Infrastructure

Entergy Louisiana building substation, upgrading infrastructure in the Carlyss area

Entergy Louisiana is in the process of upgrading infrastructure and facilities in the Carlyss, La. area.

The company is building a new substation along Carlyss Drive in Carlyss, constructing four distribution powerlines, and upgrading other line segments to support residential growth in the area. It will also benefit customers in nearby Choupique and Sulphur by reducing stress on substations in those areas.

“I’ve spent a lot of time working at Entergy in this part of Calcasieu Parish and have been fortunate to see it grow over the years,” Calvin Thibodeaux, Entergy Louisiana customer service manager, said. “This project is a win-win for Carlyss, Choupique, Sulphur and the surrounding areas because it will not only provide power to new customers in the area, but it will also provide more reliable power to existing customers.”

The Thompson substation is expected to be finished by sometime in July, while the rest of the work will be finished by October. Crews will be setting new poles in the ground and installing new wire and other electric equipment to provide electricity from the substation to area homes and businesses. Also, they will be upgrading some existing distribution lines along Carlyss Drive and Thompson and Walker roads.

“As a commissioner and someone who calls Southwest Louisiana home, I’m always excited to see great things happening across the district I serve, and that includes new infrastructure being built to support economic growth and the demand for power,” Commissioner Mike Francis, who represents District 4 on the Louisiana Public Service Commission, said. “I look forward to seeing the completion of this project and the continued growth in Calcasieu Parish.”

Dave Kovaleski

Recent Posts

NERC makes recommendations for proactively meeting power challenges this summer

The power industry and policymakers should consider implementing several recommendations now to meet expected supply shortfalls prior to the start…

1 day ago

National Renewable Energy Lab uses robots to aid wind turbine blade manufacturing

Looking to cut down on the difficult nature of the work for humans and improve consistency of the outcome, the…

2 days ago

Switch to LED streetlights could save Sylvania, Ohio nearly $77,000 annually

Toledo Edison this month began a massive streetlight conversion project through Sylvania, Ohio, installing the first of 1,650 LED replacements.…

2 days ago

Southern Nuclear names new CEO and chairman

Peter Sena III has been named the new chairman and CEO of Southern Nuclear, a subsidiary of the Southern Company.…

2 days ago

Argonne National Lab to build R&D facility to test large-scale fuel cell systems

The U.S. Department of Energy’s (DOE) Argonne National Laboratory (ANL) is con structing a research and development (R&D) facility to…

2 days ago

Program that offers tax credits for wind and solar in low-income communities to launch soon

A program that provides a 10 or 20-percentage point boost to the investment tax credit for qualified solar or wind…

3 days ago

This website uses cookies.