The West Virginia Public Service Commission (PSC) granted Tuesday a siting certificate to ESC Brooke County Power I, LLC to construct and operate a natural gas-fired wholesale electric generating facility of approximately 830 megawatts in Brooke County.

The project consists of two combustion turbines driving two combustion turbine generators and one steam turbine. It will be constructed in the West Virginia Division of Natural Resources’ Cross Creek Wildlife Management Area.

The power generated will be delivered to a new 345 kV three-breaker ring bus substation east of the facility that will be constructed and owned by First Energy. The facility will receive natural gas and ethane from dedicated pipelines that will be constructed and operated by third parties under contract to the company.

The estimated cost to build the project is $884 million. There will be no impact to West Virginia ratepayers.

The company expects that the project will create approximately 400 construction jobs and 30 permanent operations jobs. The economic impact on the state is projected to be approximately $1.8 billion during construction and $600 million in the first year of operation. The facility has an expected operational life of 30 years.

The company entered into Payment in Lieu of Taxes (PILOT) agreements with the Brooke County Commission and the Brooke County Board of Education and a lease agreement with the Brooke County Commission for the project

Construction is expected to be completed in the fourth quarter of 2020. The facility is expected to enter operation by January 2021.

Kevin Randolph

Recent Posts

Long-awaited FERC transmission planning rule tackles interregional planning

The Federal Energy Regulatory Commission (FERC) approved in a 2-1 vote the first transmission policy update in more than a…

18 mins ago

Consumers Energy to install nearly 3,000 line sensors, other smart technology this year

In a bid to improve electric reliability in Michigan, Consumers Energy recently announced plans to invest nearly $24 million to…

8 hours ago

PJM Interconnection, MISO to collaborate on interregional study

PJM Interconnection and the Midcontinent Independent System Operator (MISO) will collaborate on an informational interregional transfer capability study. The study,…

8 hours ago

Defense Department partners with Dominion Energy to meet federal carbon-free electricity goals

The U.S. Department of Defense (DoD) is working with Dominion Energy Virginia (Dominion Energy) to jointly achieve the carbon pollution-free…

8 hours ago

Duke Energy CEO lays out accomplishments at shareholder meeting

Duke Energy CEO Lynn Good laid out the company’s major achievements and milestones last year at the annual shareholders meeting…

1 day ago

Hawaiian Electric finishes work on backup transmission line for West Maui customers

Following the devastating 2023 fires, Hawaiian Electric recently completed work on a critical transmission line to offer backup power to…

1 day ago

This website uses cookies.