Duke Energy Florida files to recover investment costs associated with new natural gas plant

Duke Energy Florida filed a request Monday with the Florida Public Service Commission (FPSC) to recover investment costs associated with a new natural gas plant to be located in Citrus County, Florida.

The 1,640-megawatt combined-cycle, two-unit plant will use natural gas to provide energy to 1.8 million Florida customers in 35 counties.

Unit 1 and unit 2 are on track to begin serving customers in September and November, respectively.

If the FPSC approves the proposed changes, residential customers’ base rate would increase by $3.59 for unit 1, starting with the October billing period. Commercial and industrial customers would see a 2.5 to 3.5 percent increase.

For unit 2, residential customers’ base rate would increase by $2.25, starting with the December billing period. Commercial and industrial customers would see an increase of 1.5 to 2.1 percent.

Once the new plant is operating, Duke Energy Florida will retire its Crystal River coal-fired units 1 and 2, which were built in 1966 and 1969, respectively. The two units make up half of the company’s coal-fired power plants in Florida.

“Our customers expect and deserve cleaner energy, and building highly efficient natural gas infrastructure is critical to delivering on our commitment to a low-carbon energy future,” Harry Sideris, Duke Energy Florida president, said. “Natural gas is also an important part of our modernization strategy to continue delivering energy that is cleaner while meeting the growing energy needs of Floridians. More than ever, we are determined to make smarter energy investments that will benefit our customers and build the cleaner energy future we all want.”

Duke Energy Florida said that it also plans to invest in new solar power plants and battery storage technology over the next decade.

Kevin Randolph

Recent Posts

Louisville Gas and Electric and Kentucky Utilities issue RFP for solar, wind and hydro

Louisville Gas and Electric Company (LG&E) and Kentucky Utilities (KU) issued a Request for Proposals (RFP) for new solar, wind,…

16 hours ago

Southern Power brings Wyoming’s first solar facility online

Wyoming gained its first solar facility this week, and Southern Power its 30th, with the beginning of operations at the…

16 hours ago

Electric Power Research Institute names three Exelon-led teams for Technology Transfer Awards

Three project teams led by Exelon engineers recently earned honors from the Electric Power Research Institute’s (EPRI) 2024 Technology Transfer…

16 hours ago

Coalition of 40 organizations urge Congress to provide funding for electric transmission

A coalition of more than 40 organizations and companies is urging Congress to provide robust funding for electric transmission deployment…

16 hours ago

Biden Administration provides guidance on Qualifying Advanced Energy Project Tax Credit

The Department of Energy (DOE), along with U.S. Department of the Treasury and the Internal Revenue Service (IRS) issued guidance…

2 days ago

Ameren Illinois to upgrade underground natural gas storage fields for reliability assurance

In a bid to diversify its energy portfolio and improve winter reliability, Ameren Illinois recently announced plans to upgrade infrastructure…

2 days ago

This website uses cookies.