Georgia Power recently announced that Southern Nuclear increased the capital and construction cost forecast for its share of the project and said that the company had made “significant progress” since assuming project management.

Based on a revised cost-to-complete estimate, Southern Nuclear increased its cost estimate from $7.3 billion to $8.4 billion. The company will absorb the additional costs, and they will have no impact on customer bills. The company has opted not to ask the Georgia Public Service Commission (PSC) to approve the increased costs, having received the PSC’s approval of the capital forecast last year.

The company also determined that the previous contingency for the project is insufficient to fully offset forecasted cost increases, resulting in an increased contingency of approximately $400 million. The company may present this to the Georgia PSC for evaluation in the future.

Georgia Power highlighted several milestones achieved recently including a major concrete placement inside the Unit 3 shield building that lasted more than eight continuous hours and the placement of a 52,000-pound Q233 piping module for Unit 4 inside the containment vessel.

“Significant progress has been made on the construction of Vogtle 3 & 4 since the transition to Southern Nuclear following the Westinghouse bankruptcy,” Georgia Power Chair, President and CEO Paul Bowers said. “While there will always be challenges in building the first new nuclear units in this country in more than 30 years, we remain focused on reducing project risk and maintaining the current project momentum in order to provide our customers with a new carbon-free energy source that will put downward pressure on rates for 60 to 80 years.”

The projected in-service dates are still in November 2021 for Unit 3 and November 2022 for Unit 4.

Kevin Randolph

Recent Posts

South Carolina legislation will help Duke Energy Progress customers save money

Innovative legislation will help Duke Energy Progress customers in South Carolina save $35 million in repair costs from a series…

9 hours ago

Appalachian Power, Wheeling Power file cost recovery submissions for West Virginia

Looking to recover costs associated with increased fuel and vegetation management expenditures, Appalachian Power and Wheeling Power recently submitted new…

9 hours ago

Hawaiian Electric launches online siting tool for electric vehicle charging stations

As a way to aid the deployment of electric vehicle charging stations, Hawaiian Electric this week released the online Electric…

9 hours ago

AEP issues 2024 corporate sustainability report

American Electric Power (AEP) released its 2024 Corporate Sustainability Report, which documents its sustainable business practices, strategy, performance and impact.…

9 hours ago

Louisville Gas and Electric and Kentucky Utilities issue RFP for solar, wind and hydro

Louisville Gas and Electric Company (LG&E) and Kentucky Utilities (KU) issued a Request for Proposals (RFP) for new solar, wind,…

1 day ago

Southern Power brings Wyoming’s first solar facility online

Wyoming gained its first solar facility this week, and Southern Power its 30th, with the beginning of operations at the…

1 day ago

This website uses cookies.