Illinois and Virginia will see the creation of two new wind and solar energy farms with enough power to charge 74,000 homes, thanks to an agreement announced this week between Apple, Akamai, Etsy and Swiss Re.

In all, their efforts will yield 290 megawatts of renewable energy added to the Eastern U.S. electric grid. Apple is spearheading the effort to help the other companies gain access to wind and solar power at competitive prices and agreement terms within the 13 state PJM wholesale electric market. In this way, they are accelerating renewable energy generation.

“At Apple, we’re proud to power all of our operations around the world with 100 percent renewable energy,” Lisa Jackson, Apple’s Vice President of Environment, Policy and Social Initiatives, said. “In the process, we’ve charted a course for other companies and organizations to purchase renewable energy and transition their own operations to greener power. The collaboration announced today shows how companies of all sizes can address climate change by coming together.”

The 3Degrees company is assisting the group. The projects should come online in the next two years, with sPower and Geronimo Energy on development.

Chris Galford

Recent Posts

EPA launches nearly $1B in grants to replace polluting heavy-duty vehicular polluters

With the launch of a nearly $1 billion Clean Heavy-Duty Vehicles Grant Program, the U.S. Environmental Protection Agency (EPA) recently…

14 hours ago

Maine Gov. Mills touts state’s offshore wind leadership at conference

During her keynote address at the Oceantic Network’s International Partnering Forum (IPF) in New Orleans last week, Maine Gov. Janet…

14 hours ago

Industry groups applaud new energy codes set by HUD, USDA

An update from the U.S. Department of Housing and Urban Development (HUD) and Department of Agriculture (USDA) on energy codes…

14 hours ago

Interconnection reform needed to keep transmission upgrades moving, industry report says

If the clean energy transition is to pick up speed, and transmission upgrades are to continue, the way interconnection works…

14 hours ago

Analysts update report on Order 1000’s impact on project costs ahead of FERC’s transmission order

The Federal Energy Regulatory Commission’s (FERC) long-awaited transmission planning and cost-allocation proposal is being considered on May 13 in a…

3 days ago

DOE issues final rule on transmission permitting

The U.S. Department of Energy (DOE) issued a final rule on transmission permitting and announced a commitment for up to…

4 days ago

This website uses cookies.