The Federal Energy Regulatory Commission (FERC) recently gave Rover Pipeline, LLC approval to bring its Burgettstown and Majorsville supply laterals, along with the associated compressor and metering stations, into service.
The approval allows for 100 percent of the long-haul contractual commitments on Rover to begin Sept. 1.
Rover, a 713-mile natural gas pipeline, will transport natural gas from the Marcellus and Utica production areas to markets across the United States and to the Union Gas Dawn Storage Hub in Ontario, Canada.
When fully operational, Rover will transport gas from processing plants in West Virginia, Eastern Ohio and Western Pennsylvania for delivery to pipeline interconnections in West Virginia and Eastern Ohio. It will also transport gas to the Midwest Hub near Defiance, Ohio, where as much as 68 percent of the gas will be delivered for distribution to markets across the United States.
FERC approved Rover for the full 3.25 Bcf per day on June 1. Rover began service on the project on Aug. 31, 2017. Rover expects restoration activities along the full line to be completed by the end of the year.
The power industry and policymakers should consider implementing several recommendations now to meet expected supply shortfalls prior to the start…
Looking to cut down on the difficult nature of the work for humans and improve consistency of the outcome, the…
Toledo Edison this month began a massive streetlight conversion project through Sylvania, Ohio, installing the first of 1,650 LED replacements.…
Peter Sena III has been named the new chairman and CEO of Southern Nuclear, a subsidiary of the Southern Company.…
The U.S. Department of Energy’s (DOE) Argonne National Laboratory (ANL) is con structing a research and development (R&D) facility to…
A program that provides a 10 or 20-percentage point boost to the investment tax credit for qualified solar or wind…
This website uses cookies.