New Mexico commission approves fast-tracking of Facebook-linked solar projects

To power the expansion of a Facebook data center in Los Lunas, N.M., the New Mexico Public Regulation Commission (NMPRC) has agreed to fast-track two solar plants capable of generating 100 megawatts of renewable energy.

“By supporting industry we are putting people to work without compromising consumer protection,” Chairman Sandy Jones said. “This commission worked long and hard to bring Facebook to New Mexico and we will work just as hard to help it grow.”

The Sept. 5 vote by the commission limits the time for protests from any intervening parties to 20 days, meaning commissioners could issue a final order by Sept. 26. If protests are filed, a hearing would likely be scheduled on Oct. 17, with a final order issued October 31, the NMPRC said.

In total, the pair of facilities – to be established near Moriarty, New Mexico and Rio Rancho, New Mexico, respectively – will cost $140 million to build and provide up to 400 construction jobs in the process. The Public Service Company of New Mexico (PNM) is proposing the facilities, but they will be owned and operated by subsidiaries, through which PNM will buy energy and deliver it to Facebook.

Existing utility rates will not be affected by the move. Completion of the first facility is expected by Dec. 31, 2019 and the second should follow by June 30, 2020.

Chris Galford

Recent Posts

Program that offers tax credits for wind and solar in low-income communities to launch soon

A program that provides a 10 or 20-percentage point boost to the investment tax credit for qualified solar or wind…

15 hours ago

Business Council for Sustainable Energy voices support for crackdown on critical mineral supply chains

As the House considers numerous ways to lock China out of the U.S. market, the Business Council for Sustainable Energy…

15 hours ago

DOI grants West Virginia, North Dakota $54.2M to plug orphaned gas wells

The states of West Virginia and North Dakota were awarded $54.2 million by the U.S. Department of the Interior to…

15 hours ago

Long-awaited FERC transmission planning rule tackles interregional planning

The Federal Energy Regulatory Commission (FERC) approved in a 2-1 vote the first transmission policy update in more than a…

1 day ago

Consumers Energy to install nearly 3,000 line sensors, other smart technology this year

In a bid to improve electric reliability in Michigan, Consumers Energy recently announced plans to invest nearly $24 million to…

2 days ago

PJM Interconnection, MISO to collaborate on interregional study

PJM Interconnection and the Midcontinent Independent System Operator (MISO) will collaborate on an informational interregional transfer capability study. The study,…

2 days ago

This website uses cookies.