Florida Public Service Commission approves cost recovery for two Duke Energy Florida solar projects

The Florida Public Service Commission (PSC) approved this week cost recovery for the development of two solar projects by Duke Energy Florida, LLC (DEF).

The PSC found that the Hamilton Solar Power Plant and the Columbia Solar Power Plant are cost effective and meet the provisions of DEF’s 2017 Stipulation and Settlement Agreement approved by the PSC.

The 74.9 megawatt (MW) Hamilton Project facility, went into service in December 2018. The Columbia Project, also a 74.9 MW facility, will enter service in early 2020.

“DEF’s solar projects are forward-thinking, cost effective, and benefit customers, while producing emissions-free energy,” PSC Chairman Art Graham said. “They are a win-win for the company and for its customers, and the solar projects also defer the need for future gas-fired generation.”

The Hamilton and Columbia Projects are the first of the company’s planned 700 MW of solar production. The projected weighted average installed cost for the two solar projects is $1,486 per kilowatt alternating current (kWac). This is less than the cost anticipated in the agreement.

DEF requested the approval of $29.2 million in total annual revenue requirements for the two projects and petitioned for cost recovery through a Solar Base Rate Adjustment (SoBRA). A SoBRA enables the PSC to consider adding solar projects to a utility’s rate base without the expense of a full rate case proceeding.

Kevin Randolph

Recent Posts

NERC makes recommendations for proactively meeting power challenges this summer

The power industry and policymakers should consider implementing several recommendations now to meet expected supply shortfalls prior to the start…

19 hours ago

National Renewable Energy Lab uses robots to aid wind turbine blade manufacturing

Looking to cut down on the difficult nature of the work for humans and improve consistency of the outcome, the…

2 days ago

Switch to LED streetlights could save Sylvania, Ohio nearly $77,000 annually

Toledo Edison this month began a massive streetlight conversion project through Sylvania, Ohio, installing the first of 1,650 LED replacements.…

2 days ago

Southern Nuclear names new CEO and chairman

Peter Sena III has been named the new chairman and CEO of Southern Nuclear, a subsidiary of the Southern Company.…

2 days ago

Argonne National Lab to build R&D facility to test large-scale fuel cell systems

The U.S. Department of Energy’s (DOE) Argonne National Laboratory (ANL) is con structing a research and development (R&D) facility to…

2 days ago

Program that offers tax credits for wind and solar in low-income communities to launch soon

A program that provides a 10 or 20-percentage point boost to the investment tax credit for qualified solar or wind…

3 days ago

This website uses cookies.