Vineyard Wind project receives key approval in Massachusetts

Published on May 14, 2019 by Dave Kovaleski


Warning: Undefined variable $post_id in /var/www/dailyenergyinsider.com/wp-content/themes/dei/single.php on line 31

Warning: Undefined variable $post_id in /var/www/dailyenergyinsider.com/wp-content/themes/dei/single.php on line 36
© Shutterstock

Vineyard Wind got the approval of Massachusetts authorities to build and operate electric transmission facilities that will deliver 800 megawatts (MW) of wind energy to the regional power grid.

The approval by the Massachusetts Energy Facilities Siting Board (EFSB) represents a key milestone in the development of the first commercial-scale offshore wind generation facility in the United States.

“Approval by the Massachusetts EFSB is another affirmation of the collaborative, community-focused approach that Vineyard Wind has taken in designing and developing the nation’s first commercial-scale offshore wind project,” Erich Stephens, chief development officer of Vineyard Wind, said. “We want to thank the residents and officials of the Town of Barnstable who took the time to explore opportunities to address local concerns while simultaneously delivering enough cost-competitive, carbon-free energy to serve six percent of the Commonwealth’s electricity demand, making the project a real win-win-win.”

The Massachusetts Department of Public Utilities approved long-term power purchase contracts between Vineyard Wind and Massachusetts’ electric distribution companies in April for the delivery of wind energy.

“Today’s decision is another critical step forward as Vineyard Wind moves toward beginning on-shore construction later this year,” said Laura Beane, president and CEO of Avangrid Renewables, a partner in the Vineyard Wind joint venture. “The future of the American offshore wind energy industry is rising in Massachusetts thanks to the commitment of many stakeholders to deliver competitive solutions to climate change, and we remain committed to delivering environmental benefits and economic opportunity through our investment.”

The project moves forward as the owners seek more than 25 federal, state, and local approval processes. Reviews are still pending from the U.S. Bureau of Ocean Energy Management (BOEM), the Army Corps of Engineers, Massachusetts Department of Environmental Protection, the Cape Cod Commission, the Martha’s Vineyard Commission, and local conservation commissions.

“The EFSB’s decision is another example of how the global offshore wind experience and expertise of Vineyard Wind’s joint venture partners, coupled with the local knowledge from our growing team, is able to design and deliver a great project for Massachusetts, and create new economic growth and opportunity for the Commonwealth,” Michael Hannibal, partner with Copenhagen Infrastructure Partners, said. “Vineyard Wind’s diligent efforts to develop America’s first commercial-scale offshore wind project are centered around a firm commitment to work closely with stakeholders at the state, local, regional and national levels.”

Construction on the Vineyard Wind project is anticipated to begin in 2019 with a plan to be operational by 2021.