Georgia Power moving forward with construction milestones at Vogtle plant

Georgia Power placed the middle containment vessel ring for Unit 4 at the Vogtle nuclear expansion near Waynesboro, Ga.

It is one of several projects ongoing at the facility.

The 2.4 million-pound, 51-foot tall containment vessel ring – which consists of dozens of individual steel plates — is part of the structure that houses the reactor vessel. The middle ring is the second of three containment vessel rings to be set for Unit 4.

Additionally, the placement of more than 930 cubic yards of concrete was completed inside the Unit 3 shield building. The Unit 3 shield building is now more than 80 percent complete. The shield building is made of steel and concrete.

Workers also set the fourth and final core make-up tank for the Vogtle 3 & 4 projects. The 330,000-pound stainless-steel tank is part of the safety core cooling system to keep the reactor vessel cool. The tank was placed inside the Unit 4 containment vessel.

Finally, the last section of the steel floor that sits atop the in-containment refueling water storage tank (IRWST) has been set inside the Unit 4 containment vessel. The IRWST contains more than 500,000 gallons of borated water and provides heat removal from the reactor.

The Vogtle 3 & 4 facility employs more than 400 craft workers, mostly pipefitters and electricians, and more than 8,000 workers overall.

Once the units begin operating, the facilities will employ more than 800 permanent workers. It is owned by Georgia Power, which serves 2.6 million customers in Georgia.

Dave Kovaleski

Recent Posts

South Carolina legislation will help Duke Energy Progress customers save money

Innovative legislation will help Duke Energy Progress customers in South Carolina save $35 million in repair costs from a series…

2 days ago

Appalachian Power, Wheeling Power file cost recovery submissions for West Virginia

Looking to recover costs associated with increased fuel and vegetation management expenditures, Appalachian Power and Wheeling Power recently submitted new…

2 days ago

Hawaiian Electric launches online siting tool for electric vehicle charging stations

As a way to aid the deployment of electric vehicle charging stations, Hawaiian Electric this week released the online Electric…

2 days ago

AEP issues 2024 corporate sustainability report

American Electric Power (AEP) released its 2024 Corporate Sustainability Report, which documents its sustainable business practices, strategy, performance and impact.…

2 days ago

Louisville Gas and Electric and Kentucky Utilities issue RFP for solar, wind and hydro

Louisville Gas and Electric Company (LG&E) and Kentucky Utilities (KU) issued a Request for Proposals (RFP) for new solar, wind,…

3 days ago

Southern Power brings Wyoming’s first solar facility online

Wyoming gained its first solar facility this week, and Southern Power its 30th, with the beginning of operations at the…

3 days ago

This website uses cookies.