Utilities spent less on energy production, more on delivery in last decade

Major utilities in the United States have spent less on producing energy over the past decade but more on energy delivery, according to a new report from the Energy Information Administration (EIA).

The report found that major utilities spent 4.3 cents per kilowatt-hour (kWh) on electricity delivery in 2020, up about 65 percent from 2010. Electricity delivery includes the money spent to build, operate, and maintain the electric wires, poles, towers, and meters that make up the transmission and distribution system. The costs increased as utilities spent money replacing aging equipment, building infrastructure to accommodate new wind and solar generation, and installing new technologies such as smart meters to increase efficiency, resilience, and security.

However, utility spending on power production decreased 32 percent since 2010 to 4.6 cents/kWh in 2020. This includes money spent to build, operate, fuel, and maintain power plants, as well as the cost to purchase power in cases where the utility either does not own generators or does not generate enough to fulfill customer demand. Spending on electricity production includes the cost of fuels, capital, labor, and building materials, as well as the type of generators being built.

This year, the demand for consumer goods and the energy needed to produce them has been outpacing supply. This, in turn, has contributed to higher prices for fuels used by electric generators, especially natural gas. The increased cost for fuel, capital, labor, and building materials is increasing the cost of power production for 2021.

The U.S. average electricity prices have been higher every month of this year compared with 2020, according to EIA’s Monthly Electric Power Industry Report.

Dave Kovaleski

Recent Posts

Natural gas meter replacements coming to Jefferson City, Missouri

After 20 years, Ameren Missouri will upgrade natural gas meters throughout Jefferson City, Mo., this spring, switching to modules that…

21 hours ago

U.S. Departments of Energy and Labor release national guidelines for battery machine apprentices

In a joint effort, the U.S. Department of Energy (DOE) and Labor (DOL) released National Guideline Standards for the Battery…

21 hours ago

NARUC issues new report for state commissioners on EV infrastructure funding program

The National Association of Regulatory Utility Commissioners (NARUC) released a report to help state commissions on their roles related to…

21 hours ago

Entergy Louisiana lays out strategic blueprint for building its electric infrastructure

Entergy Louisiana has developed a strategic blueprint for building new electric infrastructure that meets the needs of its service territory.…

21 hours ago

Limestone Ridge Project brings greater reliability to Southeast Missouri

In collaboration with Wabash Valley Power Alliance (WVPA), Ameren Transmission finished work on the Limestone Ridge Project at the end…

2 days ago

Consumers Energy partners with Muskegon County for 250 MW solar facility in Michigan

Beginning in April, Consumers Energy of Michigan, the Muskegon County Resource Recovery Center, and Moorland Township will work together to…

2 days ago

This website uses cookies.