Kicking off the month, Georgia Power connected Unit 4 of the Alvin W. Vogtle Electric Generating Plant to the electric grid for the first time, ticking off another test item for the nuclear expansion project on the road to a second quarter 2024 in-service debut.

Vogtle was first commissioned in 1987, but this year will see its reach grow to four units in all, located near Waynesboro, Georgia. A third unit entered commercial operation on July 31, 2023 as an emission-less addition to the facility’s power production. This month’s startup marked the first generation of electricity from Unit 4 and included successful synchronization and connection to the grid.

Unit 4 passed initial criticality testing in February, when operators began nuclear reaction inside the reactor, utilizing nuclear heat to produce steam.

Next, operators will raise reactor power for generation of electricity while performing tests at various power levels. Eventually, power will reach 100 percent, at which point startup testing will be complete and the unit will be available for reliable dispatch, officially entering commercial operation.

Once fully operational, each of the new units will be able to produce enough electricity to power an estimated 500,000 homes and businesses in the region.

Chris Galford

Recent Posts

Louisville Gas and Electric and Kentucky Utilities issue RFP for solar, wind and hydro

Louisville Gas and Electric Company (LG&E) and Kentucky Utilities (KU) issued a Request for Proposals (RFP) for new solar, wind,…

11 hours ago

Southern Power brings Wyoming’s first solar facility online

Wyoming gained its first solar facility this week, and Southern Power its 30th, with the beginning of operations at the…

11 hours ago

Electric Power Research Institute names three Exelon-led teams for Technology Transfer Awards

Three project teams led by Exelon engineers recently earned honors from the Electric Power Research Institute’s (EPRI) 2024 Technology Transfer…

11 hours ago

Coalition of 40 organizations urge Congress to provide funding for electric transmission

A coalition of more than 40 organizations and companies is urging Congress to provide robust funding for electric transmission deployment…

11 hours ago

Biden Administration provides guidance on Qualifying Advanced Energy Project Tax Credit

The Department of Energy (DOE), along with U.S. Department of the Treasury and the Internal Revenue Service (IRS) issued guidance…

1 day ago

Ameren Illinois to upgrade underground natural gas storage fields for reliability assurance

In a bid to diversify its energy portfolio and improve winter reliability, Ameren Illinois recently announced plans to upgrade infrastructure…

1 day ago

This website uses cookies.