U.S. electric power sector experienced 4 percent fewer delays in utility-scale solar projects in 2023

Fewer delays faced U.S. utility-scale solar deployments last year, according to the latest Electric Power Monthly from the United States Energy Information Administration (EIA).

Solar developers faced delays to online dates on approximately 19 percent of planned solar capacity in 2023. The year before, the average was 23 percent. While the industry could celebrate the gains, that is still more delays the industry faced on average between 2018 and 2021. Despite this, the industry added 19 GW of new utility-scale solar photovoltaic (PV) generating capacity in 2023 – a 27 percent increase over 2022 capacity levels.

Because of this, the EIA labeled solar power as the fastest-growing source of new electricity generation in the United States. It credited falling costs, tax credits and other renewable incentives for the uptick.

Citing an analysis from the Lawrence Berkeley National Laboratory, the EIA reported that the median length for solar projects has reached 25 months from signing of interconnection agreements to actual commercial operation dates. Delays can arise due to various complications, such as permitting troubles, construction, equipment testing or the availability of materials.

For solar, tariffs are a major cause of concern. Tariffs on imported silicon from China and certain companies from Cambodia, Malaysia, Thailand, and Vietnam will kick in this June, after a temporary reprieve for these critical solar PV cell and module materials granted by President Joe Biden.

As things stand, the power sector added about 6 GW of net summer solar capacity in the first quarter of this year. Another 30 GW are in various stages of development, and going forward, another 26 GW of capacity should enter service next year.

Chris Galford

Recent Posts

NERC makes recommendations for proactively meeting power challenges this summer

The power industry and policymakers should consider implementing several recommendations now to meet expected supply shortfalls prior to the start…

3 days ago

National Renewable Energy Lab uses robots to aid wind turbine blade manufacturing

Looking to cut down on the difficult nature of the work for humans and improve consistency of the outcome, the…

4 days ago

Switch to LED streetlights could save Sylvania, Ohio nearly $77,000 annually

Toledo Edison this month began a massive streetlight conversion project through Sylvania, Ohio, installing the first of 1,650 LED replacements.…

4 days ago

Southern Nuclear names new CEO and chairman

Peter Sena III has been named the new chairman and CEO of Southern Nuclear, a subsidiary of the Southern Company.…

4 days ago

Argonne National Lab to build R&D facility to test large-scale fuel cell systems

The U.S. Department of Energy’s (DOE) Argonne National Laboratory (ANL) is con structing a research and development (R&D) facility to…

4 days ago

Program that offers tax credits for wind and solar in low-income communities to launch soon

A program that provides a 10 or 20-percentage point boost to the investment tax credit for qualified solar or wind…

5 days ago

This website uses cookies.