News

Minnesota energy companies cleared to upgrade nearly 100 miles of transmission line

In a move companies heralded for its potential to reduce grid congestion and offer lower cost renewable energy throughout the upper Midwest, the Minnesota Public Utilities Commission (PUC) recently approved upgrades for nearly 100 miles of transmission line.

Line updates will take place in both Minnesota and eastern South Dakota, which will consist of installing a second high-voltage circuit on two segments of the existing Brookings County-Hampton transmission line. Affected by the decision were Xcel Energy, Central Minnesota Municipal Power Agency, Great River Energy, Missouri River Energy Services, and Otter Tail Power Company.

“This project will bring low-cost renewable energy to millions of homes and businesses, supporting Xcel Energy’s clean energy vision and Minnesota’s 2040 carbon-free law,” Ryan Long, president of Xcel Energy-Minnesota, North Dakota and South Dakota, said. “We thank the Commission and other parties for recognizing the value of this project, which uses existing infrastructure to decrease congestion on our transmission system while limiting the impact to landowners in the area.”

A new circuit will be placed on current transmission structures and run around 60 miles, stretching from the Brookings County substation near White, South Dakota to the Lyon County substation near Marshall, Minnesota. A second, 39-mile circuit will be built between the Helena substation in Scott County, Minn., and the Hampton substation in Dakota County, Minn. Xcel plans to begin work in South Dakota this month.

For the region itself, these upgrades could bring significant congestion relief, thanks to additional capacity. Wind energy from southwest Minnesota and eastern South Dakota will flow outward, meaning the market will gain additional energy without associated fuel costs. In the interim, though, power will need to be shut off along each segment of transmission line as it’s being worked on. Each segment’s construction should span several months.

Xcel said it should finish the overall project in 2025.

Chris Galford

Recent Posts

Electric industry positions to meet demand growth while maintaining affordability, reliability

Energy providers are expecting unprecedented growth in demand over the next decade, and managing that demand while providing affordable and…

1 day ago

Applications close on nearly $200M in unique PHMSA grant program to fix natural gas pipes

With the Natural Gas Distribution Infrastructure Safety and Modernization (NGDISM) grant program, the U.S. Pipeline and Hazardous Materials Safety Administration…

2 days ago

New NASEO report investigates opportunities, challenges to incorporating equity into clean energy RD&D

Looking at the state and territorial level, the National Association of State Energy Officials (NASEO) recently authored the State Opportunities…

2 days ago

Eversource wins earns 96th annual Edison Award for streamlining transmission, distribution inspections

The energy company Eversource won the highest honor in the electric power industry this week when it took home the…

2 days ago

New York Transco submits proposal to deliver clean energy from offshore wind sites

New York Transco submitted proposals to the New York Independent System Operator (NYISO) to deliver clean energy from future offshore…

2 days ago

PGE’s Pope elected EEI board chair

The Edison Electric Institute (EEI) elected Maria Pope, president and CEO of Portland, Ore.-based Portland General Electric, as its new…

2 days ago

This website uses cookies.