The expansion project at the Vogtle nuclear plant near Waynesboro, Georgia, hit several construction milestones recently, including a concrete ‘super placement’ for Unit 3 and the lift of the 237-ton CA03 module for Unit 4.

The concrete placement included 1,844 cubic yards of concrete and took 71 continuous hours. Workers poured new concrete in four areas of the Unit 3 containment vessel, the refueling cavity, the bottom of the in-containment refueling water storage tank, the west steam generator cubicle walls, and the pressurizer cubicle walls.

Unit 4’s 237-ton CA03 module is a critical part of the In-Containment Refueling Water Storage Tank (IRWST). The IRWST, a 75,300-cubic-foot tank, will be filled with borated water once the units are operational and provide passive heatsink within containment and backup cooling for the reactor vessel.

Over the last 30 days, workers also placed the CA33 floor module for Unit 3 and the Vogtle Unit 4 deaerator inside the turbine building.

More than 6,000 workers are working on-site on the expansion project.

Georgia Power, which owns 45.7 percent of the new units, recently filed a recommendation with Georgia Public Service Commission to continue work on the project. The units’ co-owners, Oglethorpe Power, MEAG Power and Dalton Utilities support the recommendation. Georgia PSC will review the recommendation and make a decision on the future of the Vogtle 3 and 4 project as part of the 17th Vogtle Construction Monitoring (VCM) proceeding.

Completion of the expansion would mark the first new nuclear units in the United States in 30 years.

Kevin Randolph

Recent Posts

South Carolina legislation will help Duke Energy Progress customers save money

Innovative legislation will help Duke Energy Progress customers in South Carolina save $35 million in repair costs from a series…

1 day ago

Appalachian Power, Wheeling Power file cost recovery submissions for West Virginia

Looking to recover costs associated with increased fuel and vegetation management expenditures, Appalachian Power and Wheeling Power recently submitted new…

1 day ago

Hawaiian Electric launches online siting tool for electric vehicle charging stations

As a way to aid the deployment of electric vehicle charging stations, Hawaiian Electric this week released the online Electric…

1 day ago

AEP issues 2024 corporate sustainability report

American Electric Power (AEP) released its 2024 Corporate Sustainability Report, which documents its sustainable business practices, strategy, performance and impact.…

1 day ago

Louisville Gas and Electric and Kentucky Utilities issue RFP for solar, wind and hydro

Louisville Gas and Electric Company (LG&E) and Kentucky Utilities (KU) issued a Request for Proposals (RFP) for new solar, wind,…

2 days ago

Southern Power brings Wyoming’s first solar facility online

Wyoming gained its first solar facility this week, and Southern Power its 30th, with the beginning of operations at the…

2 days ago

This website uses cookies.