PJM’s Board of Managers authorized on Feb. 11 changes to its Regional Transmission Expansion Plan (RTEP), resulting in a net addition of nearly $234 million in projects.
The PJM Board authorized nearly $237 million in newly authorized baseline transmission enhancement projects, including $202.37 million in Federal Energy Regulatory Commission (FERC) Form No. 715 transmission owner criteria projects and $34.6 million in PJM baseline reliability projects.
The Board also authorized the cancellation of three formerly approved baseline projects, resulting in a $3 million decrease to the RTEP.
The RTEP is an ongoing comprehensive planning process and an annually published report that identifies and coordinates the implementation of transmission upgrades and enhancements needed to maintain the reliability of the transmission system.
PJM serves 65 million people across 13 states and Washington, D.C.
Central Maine Power Co. (CMP) has exceeded performance standards set by the Maine Public Utilities Commission (PUC), according to its…
PSEG Long Island received an award recently for innovation in digital engagement. The CS Week Expanding Excellence Award for Innovation…
For the second month running, Florida Power & Light Company (FPL) will reduce customer rates, thanks to approved cuts to…
A new study by National Grid and RMI seeks to better understand how integrated energy planning (IEP) and non-pipeline alternatives…
Valley Forge, Pa.-based PJM Interconnection said Thursday it anticipates having enough resources to meet electricity demand for what weather forecasters…
Mon Energy of West Virginia will begin award negotiations with the United States Department of Energy (DOE) in coming days…