Xcel Energy recently announced that work has begun southeast New Mexico on a 240-mile high-voltage transmission line project that will link New Mexico and Texas as part of Xcel Energy’s Power for the
Plains initiative.

The first segment of the project to be worked on is a 90-mile line between Hobbs and the new China Draw substation located southeast of Carlsbad, which is expected to cost approximately $163 million.

“This is fantastic news for the people of New Mexico,” New Mexico Public Regulation Commissioner Patrick Lyons said.

Approximately 250 workers will be involved in the development of the line, and the project is expected to cost $400 million, according to Commissioner Lyons.

The project will be completed in three segments from the Hobbs Plant Substation to the new Kiowa Substation located about 15 miles northeast of Carlsbad, from the Kiowa Substation to the new North Loving Substation, located about eight miles southeast of Carlsbad and from the North Loving Substation to the China Draw Substation.

Since 2011, Xcel Energy has added over 800 miles of new transmission lines in New Mexico, Texas and Oklahoma as part of its Power for the Plains initiative. It plans to add more than 700 additional miles through 2021.

Xcel energy has also built or upgraded more than 10 substations since 2011 as part of the program and plans to have more than 25 substations built or upgraded through 2021.

Daily Energy Insider Reports

Recent Posts

Retail energy consumers will see stronger protections under newly enacted legislation

Maryland Gov. Wes Moore (D) on Thursday signed into law a bill that will bolster consumer protections — especially those…

3 days ago

Edison Electric Institute reveals seven finalists for 2024 leadership and innovation award

Ahead of final announcements in June, the Edison Electric Institute (EEI) this week announced the domestic and international finalists for…

3 days ago

NextEra Energy promotes two to executive roles

Kirk Crews was appointed to the position of executive vice president and chief risk officer at NextEra Energy. Crews was…

3 days ago

U.S. electric power sector experienced 4 percent fewer delays in utility-scale solar projects in 2023

Fewer delays faced U.S. utility-scale solar deployments last year, according to the latest Electric Power Monthly from the United States…

3 days ago

DOE releases list of potential electric transmission corridors in need of expansion

The U.S. Department of Energy (DOE) is looking to accelerate the development of transmission projects in areas that present an…

3 days ago

Avangrid gathers universities, labs, and incubators for Innovation Forum on Transformative Collaboration

Eyeing ways to advance the clean energy transition, sustainable energy company Avangrid, Inc. recently gathered a mix of universities, national…

3 days ago

This website uses cookies.